Retention basin S2
Category
A retention basin at Findel Airport
Construction of a retention basin to collect surface water run-offs from the tarmac and water used to put out fires at the Findel site.
The retention basin is composed of separate compartments. One of 9,500m3 for water run-offs from the apron of aircraft parking areas P1, P7 and P10, and another of 3,500m3 for water used to put out fires. The project also includes the laying of pipes upstream and downstream of the basin as well as replacing the electrical installations at the level of the E20 main access gate.
Part of the work was carried out within the airport’s secure enclosure, adding some administrative constraints.
Our teams also worked in collaboration with our Lean department for the construction of the first level walls and to optimise the way of working in terms of both performance speed and safety.
130,000m3
Excavated Materials
31,000m3
Formwork for Structures
13,500m3
Reinforced Concrete
2,086t
Reinforcing Bars
700m
Reinforced Concrete Pipes
Credits
A relationship of trust
Client
Administration des Ponts & Chaussées [Roads & Bridges Administration]
Projets similaires
Redesign of the Pontpierre interchange
2023
Redevelopment of the Pontpierre interchange on the A4 to improve traffic flow and safety for local residents.
Dippach-Gare bypass
2023
Construction of a 2.2 km bypass to relieve traffic congestion on the rue des Trois Cantons.
Hosingen cut-and-cover tunnel
2023
The cut-and-cover tunnel is the first section of the Hosingen bypass.
Glaasbuurgronn and Groussheck viaducts
1998
As part of the construction of the Route du Nord, Félix Giorgetti carried out numerous works including the construction of two viaducts, Glaasbuurgronn and Groussheck.